After purchasing the land, Dietz Logistik 25. Grundbesitz GmbH intended to build a new logistics centre. The planning provided for an elevation of the site by approx. 1.50 m below the ground slab, which entailed extensive earth relocations. A total of approx. 65,000 m³ of soil materials had to be relocated or delivered from outside.

Field of activity

  • Land development
  • Environment
  • Geotechnics

Order

Phase I:

  • Subsoil investigation incl. foundation consulting (September 2016)
  • Soil management concept (May 2017)

Phase II:

  • Expert monitoring of the earthworks (May 2017 to date)
  • Delivery control of externally delivered materials
  • Waste-related construction supervision, classification of excavated material relevant for disposal
  • Carrying out geotechnical tests (plate load tests)
  • Geotechnical laboratory investigations
  • Documentation

SIMILAR PROJECTS

Orienting investigation of old deposits in Tündern
Verification of the utilisation history of former drilling mud pits in Schleswig-Holstein
Orienting investigation B-Plan 320 Norderstedt